Our installation was planned for the 6th April. It did
not go altogether smoothly. A few days before,
Solarsense contacted us to arrange for the scaffolding to be
erected. The scaffolding company they used (Castle
Scaffolding) were not very domestic customer focussed. When
they arrived, they started to treat our lovely flower and
shrub border as a building site and were quite rude
when asked to walk round a path instead of through the
flower bed. Additionally the scaffolders also managed to
break several tiles on the roof as they put the scaffold up.
After complaining to Solarsense, Solarsense now say they
won't be using Castle Scaffolding again, and as a gesture
they have sent us some garden gift vouchers and will repair
the damaged roof.
The second blip was just before Solarsense were due
to install, when they advised us that they were short 5
panels (out of 22). They said their panel supplier, Romag, was
very busy and had let them down. They wanted to delay
until all 22 were in stock or alternatively put up 22 other
panels of Taiwanese origin (Solarcentury make). However we
had specifically ordered UK produced panels with a black
frame to match our slate tiled roof and reduce the carbon
footprint of our installation. Solarsense came on the
contracted date and put up 17 panels and all the electrics
within 8 hours using 2 electricians and 2 pv installers. It
was very efficient and there were no problems. The other 5
panels were due to be installed two weeks later. As our system
is two parallel strings of 11 panels, if they are not balanced
electrically apparently the output is reduced, so it was only
possible to have one string of 11 switched on. The 11 panels
worked brilliantly during the lovely sunny weather and then on
the 20th April the fitters came to attach the remaining 5
panels to the roof and they switched on all 22 panels.
The electrical equipment installed comprises an inverter,
a total generation meter and an export meter. The inverter
is in the roof space, the total generation meter is neatly
placed in the house beside our fuse system and the export
meter is outside in our electricity meter cupboard. With all
22 panels working we have been producing around 25 units a
day during this current spell of sunny weather.
We are not yet signed up to receive the feed-in tariff
as we have some paperwork to complete and send to
our electricity supplier Ecotricity. We are unsure about how
the combination of export meter, total generation meter
and mains meter are working as our analogue electricity
import meter which is over 20 years old is running backwards
as we produce! Ecotricity have told us that they will get a
digital import meter fitted in due course which will correct
the situation.